New Delhi: In a major reprieve for around 4,500 distressed homebuyers, the Supreme Court has directed that financial institutions and lending banks cannot take coercive recovery action against flat purchasers until physical possession of their properties is formally handed over.
A three-judge bench comprising Justice Surya Kant, Justice Joymalya Bagchi, and Justice V. Mohan passed the order while hearing a writ petition filed by homebuyers of the stalled “GM Infinite Global Techies Town” residential project in Bengaluru. The housing project was undertaken by Gulam Mustafa Enterprises Private Limited, a real estate firm currently undergoing insolvency proceedings before the National Company Law Tribunal (NCLT).
The affected buyers submitted before the apex court that nearly 4,500 individuals had collectively disbursed almost 95 percent of the total purchase consideration to the developer. Under the original builder-buyer agreements, the handover of completed residential units was scheduled to take place by January 2022, inclusive of the stipulated grace period.
According to the petition, the project comprises three towers—Tower A, Tower B, and Tower C. While Tower C secured an Occupancy Certificate (OC) and saw partial handovers, construction work across Towers A and B remains incomplete. The home purchasers highlighted that they have been saddled with an unsustainable double financial burden, forced to pay monthly equated monthly instalments (EMIs) on their disbursed home loans while concurrently paying rent for alternative accommodation.
Recognizing the acute hardship faced by purchasers who had already paid the lion’s share of the apartment costs in good faith, the bench emphasized that homebuyers should not face aggressive loan recovery or coercive measures in the absence of receiving their homes.
Taking note that the jurisdiction and physical assets belong to Karnataka, the top court noted that the aggrieved allottees can approach the Karnataka High Court or the Bengaluru bench of the NCLT to seek project resolution, oversight of remaining construction, and long-term financial restructuring. With the interim direction protecting the buyers from coercive financial measures until delivery of possession, the bench disposed of the petition.